29.5.2008: Week 21: Digging the tunnel from both ends |
The Grjótárgöng tunnel is now being dug from both ends. The progress in week 21 was 39 metres which leaves 1243 metres to go before the two teams meet |
| Read more >>
|
|
|
25.5.2008: Reindeer going for a swim |
Ágúst Geirsson witnessed a rare side the other day near the Fljótsdalur station. When he looked out the window he saw five reindeer brave the heavy currents of the Jökulsá river and swim across it. |
| Read more >>
|
|
|
24.5.2008: The icy reservoir |
Winter still reigns in the highland despite what the calendar says. The reservoir is still frosty although the temperatures have been rising these last days. These pictures were taken on the 23rd of May and show the icy conditions clearly. |
| Read more >>
|
|
|
20.5.2008: week 20: The tunnel floor finished |
Workers from the Icelandic contractor Hraunaveita finished concreting the floors in the Jökulsárgöng tunnel, with some 1200 cubic metres being used in the final push |
| Read more >>
|
|
|
16.5.2008: Week 19: The tunnel floor finished |
Workers from the Icelandic contractor Hraunaveita finished concreting the floors in the Jökulsárgöng tunnel, with some 1200 cubic metres being used in the final push. |
| Read more >>
|
|
|
16.5.2008: The Hálslón reservoir water level |
The water level at the Hálslón reservoir has dropped this winter by 26 metres, from 625 metres above sea level to 599 metres. About half of the water volume at the reservoir has therefore been used to produce electricity in the Fljótsdalur power station. |
| Read more >>
|
|
|
11.5.2008: The first visitors at the information centre |
The first visitors at Végarđur, the information centre for the Kárahnjúkar project were rather special. They all had four legs and horns and they arrived in a group of 25.
|
| Read more >>
|
|
|
9.5.2008: Week 18: Summer arrives with a storm |
Week 18 saw yet another stretch of bad weather keeping the workers from getting to work.
|
| Read more >>
|
|
|
2.5.2008: The largest TBM components are out |
Impregilo workers successfully transported the largest TBM components out of the tunnel despite often having only a few centimetres on each side. |
| Read more >>
|
|
|
18.4.2008: The snow halts production |
The snow at the site makes things harder for the contractors and their workers. Concrete work inside the Jökulsárgöng tunnel had to be postponed because the gravel needed for the concrete production had run out and the gravel mine was covered in snow. |
| Read more >>
|
|
|
18.4.2008: The record breakers awarded |
| The crew onboard TBM set a world record during drilling of the Jökulsárgöng tunnel that was finished on the 9th of April for their achievement the men were presented with a written document marking the record. |
| Read more >>
|
|
|
11.4.2008: Breakthrough on two fronts! |
The last section of rock was blasted inside the Kelduárgöng in the east of mount Snćfell on Wednesday just after TBM 2 had finished its task. |
| Read more >>
|
|
|
11.4.2008: TBM 2 broke through in a cloud of dust |
Echoes of cheers and congratulations resounded through the cavern at the end of the Jökulsárgöng tunnel when TBM 2 finished a historical piece of work when it completed the drilling of the tunnels at Kárahnjúkar. The first TBM arrived at the site before Christmas 2003.
|
| Read more >>
|
|
|
26.3.2008: A short way to go for the TBM |
TBM 2 had just 225 metres to go in the Jökulsárgöng tunnel at the end of Easter week so it will not be long before it will push through. The conditions are favourable but the conveyors show some wear and tear so it is up to them when the milestone can be reached. |
| Read more >>
|
|
|
24.3.2008: Peeling the TBM apart |
A crew from Impregilo is now hard at work taking the TBM apart. Last week some components of the machine were transported out of the tunnel. |
| Read more >>
|
|
|
14.3.2008: Week 10: 214 metres in four days |
TBM 2 did really well in the Jökulsárgöng tunnel in week 10, drilling some 214 metres in just four days, from the 3rd to the 6th or 39 to 63 metres per day. |
| Read more >>
|
|
|
13.3.2008: The testing of the turbines |
Turbine 1 at the Fljótsdalur powerstation was again hooked up to the national grid on the 1st of February after it had been reconfigured in order for it to work as was first intended. This concludes the testing of the turbines and now all of them are ready for work. |
| Read more >>
|
|
|
7.3.2008: Week 9: Less than 900 metres to go for the TBM |
TBM 2 drilled 670 metres last February. All in all it has drilled 7,6 kilometres or 90% of the Jökulsárgöng tunnel. Now the machine only has some 900 metres to go. |
| Read more >>
|
|
|
7.3.2008: Iceland covered in the National Geographic |
National Geographic magazine devotes 28 pages of the March edition to Iceland, with the main topic being the land, the people and the contradicting views that Icelanders have on Big Industry, the aluminium smelter at the Reydarfjörđur fjord and the Kárahnjúkar plant. |
| Read more >>
|
|
|
29.2.2008: Week 8: Decent weather again last week |
The workers at Kárahnjúkar were blessed with decent weather for the second week running. Despite the temperature being below zero for the whole week and the occasional snow storm the weather was good compared to January and the beginning of February. |
Read more >>
Inside the headrace tunnel. Pictures taken by Kevi
|
|
|
16.2.2008: Week 6: Drill crews unable to get to work due to bad weather |
TBM 2 drilled some 130 metres last week, a length that has to be regarded as a pretty good achievement considering that the drill crews were unable to enter the tunnel because of bad weather twice this week. |
| Read more >>
|
|
|
22.2.2008: Week 7: Full steam ahead at the Jökulsárveita diversion |
Work at the Jökulsárveita divesion is in full swing again after slowing down for the last few weeks because the contractor ran into financial difficulties. The result was that a new company owned by Landsvirkjun has overtaken the project. |
| Read more >>
|
|
|
14.2.2008: Week 5: Winter affects the progress of the project |
The winter conditions caused problems in week 5 with TBM 2 stalling for a whole day due to bad weather. The machine did alright on the other days of the week and drilled some 130 metres. |
| Read more >>
|
|
|
14.2.2008: Hraunaveita picks up where Arnarfell left off |
Hraunaveita ehf. a new subsidiary of Landsvirkjun has begun work at the Jökulsárveita diversion site to the east of mount Snćfell. The company took over the contracts held by Arnarfell and the majority of the Arnarfell employees are now working for the new company. |
| Read more >>
|
|
|
14.2.2008: An ambulance equipped with Aurora Borealis! |
Blue and blinking lights are the standard fare on ambulances when there is an emergency. Judging by this picture however, this particular one came equipped with Aurora Borealis! |
| Read more >>
|
|
|
30.1.2008: Week 4: Almost 200 metres drilled in a week |
TBM 2 made good progress in the Jökulsárgöng tunnel drilling some 197 metres. Once it went 40 metres in a day and twice it went 35 metres. This is quite an achievement specially because delays due to rock reinforcement procedures and maintenance that occurred every day of the week |
| Read more >>
|
|
|
24.1.2008: Landsvirkjun to overtake the Arnarfell contracts |
Landsvirkjun will overtake the contracts of the Icelandic contractor Arnarfell for the construction of the Hraunaveita diversion. A statement issued by Landsvirkjun last Thursday reads: |
| Read more >>
|
|
|
24.1.2008: Revised profitability assessment regarding Kárahnjúkar Power Plant |
Landsvirkjun has revised is profitability assessment regarding Kárahnjúkar Power Plant, originally made at the end of 2002 when the decision was taken to enter into an agreement with Alcoa to build the hydroelectric installation. |
| Read more >>
|
|
|
23.1.2008: Week 3: Good conditions result in long distances |
TBM drilled 145 metres of the Jökulsárgöng tunnel in week 3, exactly the same distance and in the week before. The conditions are good and the going is good. |
| Read more >>
|
|
|
7.1.2008: Week 2: TBM 2 drilled 145 metres in week 2, the longest distance in a week since last September. |
Conditions have called for time consuming rock reinforcements using shotcrete and steel resulting in slow progress for the machine. Drilling was exceptionally good last August and September but then worsening conditions slowed things down, especially in late November and December. |
| Read more >>
|
|
|
|
 |
|
 |