Week 29: The Impregilo camp is disapearing
Week 28: Fifty workers from Ístak at Kárahnjúkar
Week 27: Halfway to go at the Grjótárgöng tunnel
Halfway to go at the Grjótárgöng tunnel


   Challenges and completion phase of the Kárahnjúkar project
 
Kárahnjúkar weather
 
East Iceland Sustainability Intitative
 

 Week 30: Tourists show great interest in the Kárahnjúkar project
Thursday July 31. 2008
Prenta textann

Many visitors came to the Kárahnjúkar area in July, more than was expected even. The Hálslón reservoir and the dams obviously attract tourists and the staff on site has remarked on how the visitors seem enthusiastic and positive the majority of the guests have been.   Shotcrete operations were carried out in the Jökulsárgöng tunnel in week 30 and work was also done at the buildings outside and at the intake and overspill at the Ufsarstífla dam.

35 thousand square metres were added to the Kelduárstífla dam and boulders were put in place to form a protective wall on the dam. Valve equipment was installed at the Kelduárgöng tunnel outtake by the Slovenian contractor Montavar.

Contract-2008

Progress week 30

 Progress so far

 %

Total size 

 KAR 24 Grjotá River Tunnel  62 m  963 m  57.8  1,665m
 KAR 24 Ufsarstifla dam  0 m3  535,000 m3  99  540,000 m3
 KAR 24 Kelduarstifla dam  35,000 m3      700,000 m3